Thomas Mesh PMP Snr Project Controls Engineer fmesh@me.com - (832) 552-2986 Over 9 years
of experience in the management and execution of the engineering,
fabrication, construction and operations aspects of oil and gas and
petro-chemical projects. The broad spectrum of experience in all areas
provides insight into the requirements of all stakeholders, applicable to the
mega-project development and execution. Highly proficient in planning and
scheduling, Earned Value Management (EVM), Critical Path Method (CPM),
schedule integration and analysis, quantity and man-hour estimating for construction
work packaging, construction progress, productivity tracking and reporting,
materials management and heavy logistics. Project development experience includes working
from the FEEP/FEED phases thru detailed design and execution from both
project management and construction roles. Experienced in all phases of
engineering processes including conceptual design, optimization, detailed
design, 3D model development, constructability and procurement. Extensive
experience utilizing Primavera and SAP. WORK
EXPERIENCE Snr Project
Controls Engineer Suncor Energy Feb 2014 – Present • Lead the
development and creation/modification of the WBS in SAP to align with the
projects execution plan. • Maintain
system and user status in SAP. • Load EDS
estimate in SAP at the lower level WBS per the EDS estimate (plan version
WBS). • Follow the
current Project Change Notice Process and maintain changes in SAP on plan
version PSC, as well as your change log. • Maintain FAC
in SAP on plan version FAC. • Support the
completions of requisitions forms for project teams. • Monitor and
control cost to the EDS estimate PO's for material, services and Staged Labor
utilizing third party reporting as provided. • Escalate
cost issues to the appropriate level. • Develop and
maintain total project cash flow by month that is supported and backed up by
the project schedule. • Lead the
monthly project accrual efforts per the process. • Develop and
maintain a level three resource loaded logic driven project schedule for each
of your projects. • Assure
contractors schedule "engineering and construction" are in
alignment with the project teams master schedule. And assure they are of
quality completeness and progress able. •Assure
contractors progress reporting is quantity based so to provide a higher
quality in reporting and predictability. •Supported the development of scheduling
standards and procedures. Worked with managers and leads to plan and develop
a detailed construction schedule, while incorporating DOW master
schedule. Established detailed schedule development, including the work
breakdown structure (WBS) and established the proper workflow logic ties
utilizing Primavera. Prepared progress curves, man-hour forecast, and
manpower histograms and developed Look-Ahead schedules. Developed
project level activity codes for the project coded by construction areas,
contracts, and process areas. Assumed other responsibilities as
required by the immediate Manager or Construction Manager. Project
Planner/Scheduler New Gold Inc - Kamloops, BC - October 2010 to December 2013 Worked
directly with the Project manager and team leads to develop (WBS) work
breakdown structure and schedules, to
ensure that all project requirements are in place, tracking through planning
stage to project or phase closure
using Primavera and Microsoft Project. •Developed a
resource loaded Engineering Procurement and Construction schedule. Review
sub-contractor schedules to
ensure compliance with agreed procedures. • Create
bi-weekly and monthly reports based on analysis of the overall project
schedule and tracks against the baseline,
specifying areas of variance and recommended remedial action to the Project
Manager. • Prepare and
issue progress reports in a clear and easily interpreted format such as S-Curves
and Histograms. Discuss
variances and delays with the project manager and recommend mitigation plans
to avoid negative impact on
project schedule and cost • Performed
critical path analysis, generated look-ahead and variance reports against
project and previous update
baselines for Process, Mechanical, Piping, Civil, Structural, Electrical,
Instrumentation work •Provided
accurate, clear and timely status reporting to senior business executives and
facilitated all related planning
development sessions Project
Planner Savcom Energy
Limited - Aberdeen - January 2009 to September 2010 Client: Gramen
Petroserve Limited for Shell Petroleum Development Company East Project:
Integrated Pipeline construction, Maintenance, Upgrade & Repair Services.
And construction projects. • Develop
& maintain project schedules as necessary to manage several active
projects, driving all resources to deliver
project goals to tight timescales. •Review of
change orders for schedule and cost impact, utilized project
management/earned value techniques to analyze
project cost variance (CV), schedule variance (SV), cost performance
indicator CPI) and schedule performance indicator (SPI). Assembling project
plans and teamwork assignments •Directing and
monitoring work efforts on a daily basis, identifying resource needs,
performing quality review; and escalating
functional, quality and timeline issues appropriately • Maintaining
a full set of documentation as required by the Project Management Process for
each project • Attending
progress meetings with project management team, subcontractors to review and
approve baseline schedules and
attend other scheduled meetings as necessary to stay current on schedules •Established
requested project plans for the execution of work in accordance to standards
and company WBS structure •Tracking
progress of multiple phases of project which includes Pre-Feed, Feed and
detailed engineering, procurement,
construction using Primavera P6 and Microsoft Project • Planning of
work in conjunction with the project team, customer and customer specific
requirements • Update and
issue weekly/monthly any status reports, milestones plans etc. as specified
by customer requirements
or the project manager. • Creation and
maintenance of networks and activities within the project WBS • Calculate
man hours on project, prepared and maintain project control Project/Scheduler Carin Energy
Limited - Aberdeen - August 2007 to December 2009 Project
Planner •Monitored a control schedule for a project or phase and the timely
prediction, control, reporting, and completion of progress against the
control schedule and assessed the criticality of the schedule achievement. •Developed a network logic schedule incorporating client’s and
subcontractor schedule data. •Updated and issued a monthly/weekly schedule, including bar charts,
s-curves and histograms as agreed upon with the client to provide the
required information on progress and performance. •Monitored interdependency of the various project activities especially
those that may form the critical path for the project. Ensured that the
current schedule was updated and reflected progress. Ensured accurate
and regular monitoring of planned progress versus actual progress. •Updated the deliverables status report to reflect the documents status
that were approved, in workflow, cancelled, not approved, approved with
comments, and issued for design. Conducted regular assessments of the
forecast milestone dates against the baseline schedule, including early
warning of potential deviations. FALKLAND OIL -
February 2005 to 2007 Perform
ongoing schedule analyses, critical path analyses, earned value analyses,
risk analyses reporting, evaluate /recommend
schedule improvement opportunities • Prepare and
present detailed planning information (Gantt charts etc.) for use by project
team • Liaise with
project team, internal departments and other functional planners to obtain
critical planning information
required to update and progress project plans • Analyze
updated plans and highlight any areas of risk or schedule conflict to the
project manager • Report
slippages against project baseline and advise potential impact on project
critical activities • Calculate
critical path analysis and identify potential problem early and give
corrective actions to put the project back on planned schedule and within
management requirement and project scope. • Conduct
project planning and post implementation review to ensure project is on
track. • Planning and
scheduling project activities and sequencing those activities from conception
to completion EDUCATION BA in Business
Economics University of
West London - London ADDITIONAL
INFORMATION Key Skills Primavera P6 MS Project Agile
Methodology SAP Materials
Management Core
Competencies * Microsoft
Office Application /Microsoft Project. * Proficiency
with Primavera software P3 and P6. * Preparing
Project WBS, Project Planning Procedure, Progress Measurement Methodology
& Project Coordination Procedure. * Logical
approach in sequencing activities and providing innovative solutions to
planning and scheduling problems. * Progress
Monitoring using Progress S- Curves, Gantt charts. * Excellent
verbal and written communication skill * Ability to
prepare clear and concise reports, procedures, correspondences, and other
written materials. Modules: PMP Training Project
planning and control, performance, planning and decision making, project
fundamentals, project organization
and behavior, Advance Strategic project management and leadership. Project
Management College, UK Software: MS
Office (Word, Excel, Project, Visio, Outlook, Access, Power Pt.) Scheduling and